EMW provided over 50 units of equipment for the reclamation works on the New Doha International Airport between 2006 and 2007. The new airport was built on land that was reclaimed for the sea and a total of 22 km2 of new land was created and built up to a final level of +4.0m. 40% of this land was to be reclaimed from the sea. The milestones were extremely tight but all milestones were reached on time.

EMW’s scope of Works:

  • Dry earthmoving for the main dredging contractor
  • Reclamation
  • High Energy Impact Compaction
  • Bund Construction
  • Rock Revetment Installation
Project details
Client JV – QDC, Boskalis,Dredging International and Great Lakes
Period 2006-2007
Location Doha, Qatar
Type of activities
  • Dry Earth Moving
  • Land Reclamation
  • Compaction