The project is located 120 km offshore from Abu Dhabi. The project consists of the construction of 2 artificial islands that are 7 km apart. EMW was involved in reclamation of land, installation of rocks, creation of concrete revetment and compaction.

EMW’s scope of Works:

  • Excavation works
  • Placement of armour rock
  • Installation of concrete Acropodes
  • Rock armour 3-5 t
  • Vibro-flotation deep compaction of 10,000,000
Project details
Client Dredging International-MEDCO Joint Venturees
Period 2011-2014
Location 120 km offshore from Abu Dhabi city
Type of activities
  • Excavation
  • Compaction
  • Hauling
  • Crane rental
  • Breakwater and revetment construction